Thursday, 24 February 2022 10:27

Smart approach loads-out modules three days early

Written by
Rate this item
(0 votes)

2,200t moves engineered in short timeframe, protecting project schedule

Offshore construction specialists Estaleiros do Brasil Ltda. (EBR) needed the load-out of seven modules to be engineered, planned, and executed in the space of just a few weeks. These modules were being built in Brazil destined for FPSO integrations abroad; the challenge was on to have the modules in active production as soon as possible.

2022 02 24 102627

The modules – some weighing up to 2,200t each and over 30m by 18m in size – were to be transferred from the quay to a waiting ship. Phase one of the project would transfer the first four such modules, and phase two the remaining three.

The work was not straightforward, however. A challenge presented itself during the first phase, as there were limited feasible jacking points available underneath the module. These are strengthened areas, built into a module’s design, that allow it to be lifted from underneath by large jacking systems.

As there was not sufficient time to reinforce the structure of each module so that they could be jacked down using other points, an alternative solution had to be found. It came through innovative use of standard lifting equipment.

Mammoet teams use trailers for 2,200t module load-out. Mammoet teams use trailers for 2,200t module load-out.

Hydraulic trailers used for transport projects have the ability to raise and lower mechanically, so it was decided that each module would be lowered sequentially, using the hydraulic course of the trailers rather than traditional jacking equipment. In turn, each module was weighed, jacked-down to the correct grillage height, then loaded-out onto the ship within a precise timeframe.

Despite the novel approach, this methodology allowed the first four modules to be loaded-out in just twelve days instead of the allotted 15.

Phase two of the operation, which included the three final modules, was successfully completed a few months later. During this phase, only the weighing and load-out was required. To complete this scope, Mammoet's team mobilized the same 96 axle-lines of PST/THP trailers as previously used, a large selection of weighing and auxiliary equipment, and it could mobilize staff from every corner of the Americas to ensure the job was done on time.

2022 02 24 102715

During phase two, the largest module measured over 29.9m (around 98,000 ft) long and 37.488m (122.9 ft) tall. Again, each module’s weight aligned with expectations, at around 2,200t each.

Mammoet Project Manager, Alvaro Campos, explains, “One of Mammoet’s greatest challenges was the mobilization time since we were asked to deliver with very short notice and the required equipment was in various locations across Brazil.

We managed to get everything to site on time thanks to the hard work of a very professional crew and we pulled out a safe execution which was praised many times by our final clients and brought them much relief.”

Both phases were effectively delivered for end customers Modec and Cameron/SBM respectively, and all tasks were executed while complying with our customer’s and Mammoet's high safety standards. Mammoet’s team has vast experience in loading out large modules onto vessels across the globe, most recently a nearly 4,000t topside in Turkmenistan.

Mammoet
Mammoet helps clients with Smarter, Safer and Stronger solutions to any heavy lifting or transport challenge. We aim to develop long term relationships in order to understand their businesses and challenges best, so we can realize the most efficient and cost-effective approaches. We have a unique global network and an unparalleled fleet of equipment. Through deep and longstanding engineering expertise and the highest quality and safety standards in execution we bring an intelligent and flexible approach to projects across a wide breadth of industry sectors. Clients trust us to help them achieve feats that were once considered impossible, and we have often broken records in doing so.

For more information, visit www.mammoet.com

Read 937 times